10/1/2013: Day 87 - Inspections Are Coming, Inspections Are Coming

I'm told that final inspections for mechanical, electrical and plumbing are scheduled for this week.  The water is now on and we can wash our hands and flush. Though, we've not started using the house.  I also noticed that the portable toilet left the site today.  Tim patched the plaster below the sink in the half bath and finished the grout in the foyer, half bath and coat closet.  Heating registers were installed in the second floor rooms.  The owners installed the shower rod and curtain in the master bath and we're starting to look finished upstairs.

Shauna prepped the kitchen for paint a few days ago and today, the primer went on.  Color looks pretty good with the existing cabinets, countertops and backsplash tile.  Big debates going on regarding front sidewalks which is next big item by us.  Thankfully a concensus/compromise was achieved and layout will continue.  That will be the next big item after paint is complete.
Kitchen gets some color (even with tinted primer only)


Foyer grouting complete

Plaster patching at Office.

Foyer grout

Plaster patch at half bath sink piping adjustements

Master Bath shower curtain is in! how's that for excitement.

Heating register and exhaust fan at Master Bath

Foyer tile grouted, from stair.

Half bath sink removed for plaster patching. faucet is temporary until selected unit arrives.