Total Pageviews
Thursday, August 29, 2013
Tuesday, August 27, 2013
8/26/2013: Day 51, Monday - Plaster Completion
Day 51 - Plaster Finishes
Day 51 brings completion to the plaster application, one of the last major milestones before finishes commence. The plaster crew arrived at 4:30am for the start of a long day in an effort to complete the remaining plaster work in a single day. It seems there was success. All areas are now finished and the beginning of the 30 day cure time can begin. This is a necessary wait time to facilitate paint adhesion. Much debate was had over the cure time and we'll see if we end up closer to 3 weeks. Wood floor, window trim and wall base profiles have been selected and Tim will begin to procure those materials. A minor correction was made to the rear deck framing today which will allow the deck boards to be installed by the blogger over the long weekend.
The vinyl siding at the chimney has been adjusted to match the now vertical chimney, and all siding odds and ends are completed except at the electrical meter. Shauna purchased a large majority of the lighting fixtures over the past weekend and we have all but the back door light ready for install when the electricians arrive for finish work in a few weeks.
We've turned a corner and the end is in sight. There's even talk of, dare I say, early completion. Alot of work is up to us at this stage including the deck boards and painting.
Day 51 brings completion to the plaster application, one of the last major milestones before finishes commence. The plaster crew arrived at 4:30am for the start of a long day in an effort to complete the remaining plaster work in a single day. It seems there was success. All areas are now finished and the beginning of the 30 day cure time can begin. This is a necessary wait time to facilitate paint adhesion. Much debate was had over the cure time and we'll see if we end up closer to 3 weeks. Wood floor, window trim and wall base profiles have been selected and Tim will begin to procure those materials. A minor correction was made to the rear deck framing today which will allow the deck boards to be installed by the blogger over the long weekend.
The vinyl siding at the chimney has been adjusted to match the now vertical chimney, and all siding odds and ends are completed except at the electrical meter. Shauna purchased a large majority of the lighting fixtures over the past weekend and we have all but the back door light ready for install when the electricians arrive for finish work in a few weeks.
We've turned a corner and the end is in sight. There's even talk of, dare I say, early completion. Alot of work is up to us at this stage including the deck boards and painting.
Thursday, August 22, 2013
Wednesday, August 21, 2013
8/20/2013: Day 45 - Plaster Board Begins
8/19/2013: Day 44 - No More Laundry & Board Arrives
Subscribe to:
Posts (Atom)